LEWALLEN BRIDGE REPLACEMENT PROJECT UPDATE
Lynn Murphy (Project Coordinator)
At month 23 of the 36 month project:
Structures:
Abutment # 1:
Good progress has been made during the past four weeks. A visiting crew was assigned to this structure alone and they have installed the engineered walls and the compacted crushed stone backfill. Work will now begin on building forms for a concrete cap, which will be poured across the exposed tops of the steel beam pilings. This cap will bear the weight for the last nine steel girder beams.